Phrases Used for Technical Performance Measures

Herding Cats

All project progress is measured independent of resources expended - Mr. Gary Bliss, Director Performance Assessment and Root Cause Analysis (PARCA), US Department of Defense. No matter the domain, the engineering development process, these concepts are applicable.

Project Management, Performance Measures, and Statistical Decision Making

Herding Cats

There is a current rash of suggestions on how to improve the performance of software projects. In this domain, we are guided by credible results using principles, processes, and procedures to increase the probability of program success.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

What Is Corporate Governance & How Can it Impact My Project?

ProjectManager.com

While making money is the overriding mandate of any for-profit enterprise, each individual organization is governed by its own set of standards and practices. Those standards and practices are called corporate governance, and they are going to influence your project.

A Compendium of Works to Increase the Probability of Project Success

Herding Cats

Managment Processes. Project Governance. Integrated Master Plan: The Foundation of Program Success , College of Performance Management, May 21, 2014. The Nine "I's" of Program Success ," College of Performance Management. Project Performance Management. Governance.

2003 59

Compendium of Works to Increase Probability of Project Success

Herding Cats

Management Processes (#MP). Project Performance Management (#PPM). Technical Performance Measures (#TPM). Cost, Schedule, and Technical Performance Management (#CSTPM). Governance (#Governance). Management Processes. Governance.

2003 45

Increasing the Probability of Project Success

Herding Cats

This means having a set of Principles, Process, and Practices to test the suggestion against. These Five Immutable principles are time phased into Processes that provide answers to the Five Principles. With some details for each process area.

2017 90

Project Versus Product in Agile Development

Herding Cats

But if the development work is a Project is a fixed period of performance, for a fixed (with margin) budget, and a fixed set of Capabilities, then the question is can agile be used to develop the software? Go write code that every few weeks produces value to the next step in the process.

Agile 50

How to Talk About Estimates

Herding Cats

We can't talk about estimates or estimate, without also talking about the precision and accuracy of the estimate (the noun) after we have performed the estimate (the verb). . What is an estimate?

People Versus Process

Herding Cats

At the program level and above, the choice of a people focus or a process focus is not between two competing paradigms. This is obvious but many times lost when discussing agile processes. One school emphasizes people, while the other emphasizes process.

Biases in Project Management and How to Remove Them

Herding Cats

Cognitive bias - a mistake in reasoning, evaluating, remembering, or other cognitive processes, often occurring as a result of holding onto one's preferences and beliefs regardless of contrary information. Because of that, we don't separate the thinking processes into a dual-system.

Value First, Requires Margin and Contingency

Herding Cats

The principles of microeconomics of decision making in the presence of uncertainty mandates you make estimates of how to achieve that Value in terms of cost and schedule, those three (and all) variables are random variables, usually driven by a stochastic process.

4 Fallacious Reasons to Estimate and Why Those Are Fallacious

Herding Cats

I need an estimate because… I need to measure productivity. Although I understand measuring productivity could work well for repeatable activities, it's hard to believe it works well for abstract and, ultimately, non-repeatable tasks like software development.

Connecting "What" with "How" - and the Failure to Understand the Principles of Systems Engineering and Systems Management

Herding Cats

It is applied through the application of systems engineering processes within a managed lifecycle working with a number of other management, engineering, and specialist disciplines. Progress and Value are measured with the same in Earned Value Management. The Measures of effectiveness.

From Mission Capabilities to Done

Herding Cats

No matter the project domain or the technical development method, project success is dependent on knowing what Done looks like in units of measure meaningful to the decision maker. These measures are stated in units, meaningful to the buyer.

2017 46

Increasing the Probability of Program Success

Herding Cats

We're working on a White Paper for the Joint Space Cost Council which is an organization composed of government (NRO, NASA, USAF, and others) and industry representatives with an interest in space. Top Four Sources of Unfavorable Program Performance. System Engineering Processes.

INVEST, Scrum and Enterprise IT

Herding Cats

That means the system architecture, the process flow, the data flow architecture components all how NO dependencies on other. a digraph like this, that model sequential, parallel and coupled process. Actual software process flows contain loops.

SCRUM 40

Risk Management in Five Easy Pieces, with Apologies to Jack

Herding Cats

Managing Cost, Schedule, & Technical Performance Risk Is The Basis Of Good Project Management. Certain information about key project cost, performance, and schedule attributes are often unknown until the project is underway. Risk Management Process Model.

Risk 48

Fallacy of the Day

Herding Cats

Project Controls are Management Actions, either preplanned to achieve the desired result, or taken as a corrective measure prompted by the monitoring process. The units of measures of Cost and Time are straightforward. Value to the business can be defined using these measures.

2017 44

Misinterpretations of the Cone of Uncertainty

Herding Cats

The Cone of Uncertainty as a Technical Performance Measure. Active reduction requires we have a desired reduction goal, perform the work, and measure progress toward the rduction goal. Closed Loop Control, has a goal, an action, a measurement, and a corrective action.

2017 42

INVEST, Scrum and Enterprise IT

Herding Cats

That means the system architecture, the process flow, the data flow architecture components all how NO dependencies on other. a digraph like this, that model sequential, parallel and coupled process. Actual software process flows contain loops.

SCRUM 36

Five Immutable Principles of Project Success

Herding Cats

No matter the engineering processes used to produce the outcomes from the project. Without these measures, Done will usually mean . Without these measures, Done will usually mean we ran out of time and money. . Physical Percent Complete is the only measure of progress to plan.

2017 46

Integrated Master Plan - Revisited

Herding Cats

Transparent – Comprehensible display of what needs to be done and how completion is measured. It is essential that the IMP represent the work that must be performed. The IMP shows the Accomplishments and the measures of Accomplishments that are essential to get through a design review.

Cone of Uncertainty Bibliography

Herding Cats

I work in a domain where the CoU is baked into the Integrated Program Performance Management (IPPM) processes flowed down from the buyer, in this case, the Federal Government. The CoU paradigm defines the needed reduction in uncertainty is some performance metric.

2017 42

Biases in Project Management and How to Remove Them

Herding Cats

Cognitive bias - a mistake in reasoning, evaluating, remembering, or other cognitive processes, often occurring as a result of holding onto one's preferences and beliefs regardless of contrary information. Because of that, we don't separate the thinking processes into a dual-system. And of course, those are biased, filtered are fed back into System One at a later date, creating more bias to the decision-making process in the future.

Closed Loop Control and Granularity of the Estimating Process

Herding Cats

For software, this can be value produced (assuming we have a unit of measure for that value in the for of effectiveness, performance, key performance parameters, or technical performance measures ). DP6Jw is an overview of this process. For your Honeywell or Nest controller on the wall, that sample rate is measured in seconds. It can be the cost, schedule, and technical performance measures of the software project.

Project Status Reporting – 6 Key Considerations

Project Health Check

The entire purpose of the Start-up Phase of a Project is to produce a comprehensive Plan for the Project; consisting of an integrated Performance Measurement Baseline (Time, Cost, Scope) and an associated Project Management Plan to monitor and control it. Governance Status Reporting

2017 250

Do you know, really know….?

Ron Rosenhead

The project manager had no view at all of his performance and no development needs were discussed. He told me that he had not had the usual performance management review nor sat with anyone to produce a personal development plan.

2017 176

Project Start-Up: The Plan for a Plan

Project Health Check

Du ring the Project Start-up and planning phase, projects will execute detailed planning processes to produce a Performance Measurement Baseline of Cost/Schedule/Scope and an associated Project Management Plan.

Physical Percent Complete: Knowing When You Are Done

Herding Cats

The goal of every program manager is to have a set of practices that connect all the programmatic planning, risk, and performance information in a single unified view needed to support the decisions that increase the probability of success of any project or program.

3 Questions That Must Be Asked at Every Project Management Meeting

Herding Cats

In the ConOps are measures of Effectiveness for the components of the project that implement the Capabilities . The only answer to that is a measure of Physical Percent Complete (P%C). These measures are supported by Quantifiable Backup Data.

2018 46

What's Missing from the Agile Software Development Paradigm

Herding Cats

The customer is accountable for knowing what Done Looks Like (in Unity of measure meaningful to their domain). The results include system-level qualities, properties, characteristics, functions, behavior, and performance. System performance requirements are testable and measurable.

Cone of Uncertainty - Part Cinq

Herding Cats

The Cone is a project management framework describing the uncertainty aspects of estimates (cost and schedule) and other project attributes (cost, schedule, and technical performance parameters). The Cone is NOT the result of the project's past performance.

2017 43

The Problems with Schedules

Herding Cats

Unrealistic performance expectations missing Measures of Effectiveness and Measures of Performance. There is a common chart used to show poor performance of projects that compares Ideal project performance with the Actual project performance.

2016 55

Cone of Uncertainty - Part Cinq (Updated)

Herding Cats

The Cone is a project management framework describing the uncertainty aspects of estimates (cost and schedule) and other project attributes (cost, schedule, and technical performance parameters). The Cone of Uncertainty describes the evolution of the measure of uncertainty during a project.

2017 40

Cone of Uncertainty - Part Deux

Herding Cats

The Cone is a project management framework describing the uncertainty aspects of estimates or any other project attribute (in this post, cost, schedule, and technical performance parameters). There can be cost and schedule performance measures as well.

2017 39

Cone of Uncertainty - Part Trois

Herding Cats

The Cone is a project management framework describing the uncertainty aspects of estimates (cost and schedule) and other project attributes (cost, schedule, and technical performance parameters). The Cone is NOT the result of the project's past performance.

2007 36

Does your organization truly support project management?

Kiron Bondale

Organizational project management support can be either a blocker in lower maturity companies or an accelerator to project performance in higher maturity ones. Objectives and performance measures for these staff should include a healthy balance between operational and project success metrics.

2016 191

What Should I Look For in a Statement of Work?

LiquidPlanner

Governance. The SOW should also talk about project governance. . Check that the change control process is documented, along with risks, assurance, and quality measures.

2020 91

Is Macroeconomics and Social Science the Same as Software Development?

Herding Cats

In our domain this is the Performance Measurement Baseline, which is a time-phased budget plan for accomplishing work against which contract performance is measured. But margin, management reserve, analysis of alternative is standard project management process of dealing with the indeterminate elements of projects. Domain and Context Are King, Then Comes Process and Experience. NoEstimates Agile Economics Estimating Governance

2016 36

Misquotes of Deming

Herding Cats

It is wrong to suppose that if you can’t measure it, you can’t manage it – a costly myth. Technical Performance Measures. It's common to misquote famous quotes. The #NoEstimates advocates love to use a Deming quote.

2016 52