Tales of an Expert Witness: Sex, Lies, and Video (Part I)

Rate this item
(1 Vote)

The subpoena shows up at the front desk and the call comes to you to pick it up. That nauseating feeling in your gut is the prelude to a long day… no… a long year. The lawyers want every contract and statement of work, each change order, log, email, document, physical mail, specification, test document, picture, drawing, scratch note, etc. that ever existed on your project. You reflect back on the project and wonder how many times you cut corners in order to get the project done. Well as "done" as it is. After all, the customer never did really accept the final product. Maybe you should have had the project health check performed.

You may think it will never happen to you, but it does—every day. Two realities, though, are certain, you cannot run your project in paranoia about every document and email you or your team sends and neither can you ignore the chance that a court may be the arbiter of the delivery. All of us have been on one of those ugly projects where we had to review the contract to determine the possible exit strategies. That is the first step in a short walk to litigation.

Never Admit A Lie; Better Yet, Never Lie.

How many times have you told that little fib? Maybe it is trivial. "We completed that today." However, you know quite well that the engineering manager promised it tomorrow. It is already two weeks late and you are anxious to get some good news to your customer.

Such a stretch sounds innocent enough. Then reality hits. The engineering group misses their delivery; you get frustrated and write a note to the project executive. You say, "To calm the client, I told them that engineering finished the job today, when I knew it would not be done until tomorrow. Now the engineering manager says it won't be done for another week!" With the delivery of the subpoena for all project documents, this email is now part of the court's evidence (part of discovery) and proves that you lied to your client. Your credibility, ethics, and character are now in question.

Contract Extension or New Statement of Work?

Although the details are deeper than this article, there is a fuzzy line between change orders and statements of work. Why do you care? A change order alters the parameters of an existing contract while a properly worded statement of work says you are effectively starting something new. The latter triggers the start of the statute of limitations while the change order does not. With the statute of limitations are implications on warranty period, implied acceptance, and limitations on liability. If you only use change orders, nothing is ever completed. As you might imagine, in a legal battle, lawyers dissect these distinctions. It is best to make sure that you define the use of each document completely and use them as defined.

Signatures Are Not Just A Formality

In litigation, signatures and dates are the Holy Grail. The absence of signatures means "failure to reach agreement." Missing signatures on specifications are fatal since that means the customer never agreed to what you were building. Absence of signatures on acceptance documents means what you were building never worked or was not acceptable. When you contend that the deliverable met the form, fit, and function you will have a difficult time convincing a jury if there are no signatures to prove it. Every deliverable must have a document with the signature of a receiving party's showing the items were satisfactory for use—even if only conditional.

Boilerplates Can Kill You

Boilerplates are great time savers. They can help fill up a proposal or SOW so that it looks impressive by its sheer volume. Their prior vetting lures you into the false comfort that they must be right and will save time and reduce frustration. They come with an inherent liability—increased risk from extraneous sections that are irrelevant in the current situation. Templates, like standards, often contain far more material than what you need for your project. Boilerplates are good as starting points to help you remember to include commonly forgotten items, but there are loaded with options, often contradictory, that may have no relevance. Accidentally leaving in two opposing sections is a lawyer's fodder to show incompetence on the part of the document's originator.

Clarity and Honesty

Clarity and honesty sum up the first part of this two-part article. It seems so simple. Company culture, financial pressures, personal achievement goals, pleasing the customer, and plain old greed, however, change how we deal with our clients. The best defense is a humble start and a truthful relationship. Although this will help to keep you out of court, lawyers will find ways to leverage your statements and actions against you. In the second part of this article, the discussion will focus on the dangers of certifications, standards, and trust relationships.

Read 29851 times

Related items

  • Filling Execution Gaps: How Executives and Project Managers Turn Corporate Strategy into Successful Projects
    What Filling Execution Gaps Covers

    Filling Execution Gaps

    by Todd C. Williams
    ISBN: 978-1-5015-0640-6
    De G Press (DeGruyter), September 2017

    Project alignment, executive sponsorship, change management, governance, leadership, and common understanding. These six business issues are topics of daily discussions between executives, middle management, and project managers; they are the pivotal problems plaguing transformational leadership. Any one of these six, when improperly addressed, will hex a project's chances for success. And, they do—daily—destroying the ability companies to turn vision into value.

    Check it out on Amazon or the Filling Execution Gaps website

    Without the foundation of a common understanding of goals and core concepts, such as value being critical to success, communication stops and projects fail.

    Without change management, users fail to adopt project deliverables, value is lost, and projects fail.

    Without maintaining alignment between corporate goals and projects, projects miss their value targets and projects fail.

    Without an engaged executive sponsor, scope increases, goals drift, chaos reigns, value is lost, and projects fail.

    Without enough governance, critical connections are not made, steps are ignored, value is overlooked, and projects fail.

    Too much governance slows progress, companies cannot respond to business pressures, value drowns in bureaucracy, and projects fail.

    Without strong leadership defining the vision and value, goals are not set, essential relationships do not form, teams do not develop, essential decisions are not made, and projects fail.

  • Kill The White Knight

    There is a reason we hesitate to teach classes on fixing failing projects. Many a cynic feels that we simply do not want to teach our trade, however, our reason is far nobler—we should be teaching prevention rather trying to create white knights to save the day. It is the same philosophy as building a fence at the cliff's edge rather than an emergency room at its base. Our language is replete with idioms telling us to look past the symptoms and address problems at their root cause. 'An ounce of prevention versus a pound of cure' or 'a stitch in time saves nine.' Please, feel free to supply your own in the comments. Unfortunately, most of our businesses loathe this philosophy, waiting to address an issue until it is irrefutably broken.

  • Tales of an Expert Witness: Sex, Lies, and Video Tape (Part II)

    Trust relationships, certifications, and standards sound like such a safe harbor. These sound like such great words in a proposal or statement of work. How could you possibly go wrong building a trusted relationship with a customer by committing to follow a standard? In fact, this can burn you… in court.

    No one ever starts a project with the goal of ending up in court. In fact, litigation may never cross your mind; after all, you have built a trusted partner relationship. Taking a few cautionary steps, however, will make your life easier if you end up in that ill-fated litigious position. Your best chances for success come long before you enter the courtroom—even before the project starts.

  • IT: We Don't Need No Stinking Leadership

    I have never posted email marketing results, because... well, let's face it... it is kind of tacky. Now and then, however, there is a story to be told. In my opinion, this set of statistics is a little over-the-top in what it shows. I can only see one way to interpret it other than Information Technology "leaders" simply do not care about leadership.

    To understand how I can make such a brash statement, you need a little background...

  • Alignment: Using the Balanced Scorecard to Create Corporate Synergies
    Alignment: Using the Balanced Scorecard to Create Corporate Synergies

    Add To Cart

    Author:Robert S. Kaplan, David P. Norton
    Publisher: Harvard Business Review Press
    Released: April 2006
    Type: Hardcover
    Pages: 320
    ISBN:978-0201835953

    Projects build capabilities to met corporate goals. If you are a CEO, you need to make sure your employees and vendors know what those goals are and how they fit in to the plan. If you are a project manager, you need to know the bounds of you project. If you are anywhere in-between, you need to understand how all the pieces fit together and keep it all aligned.

    Most organizations consist of multiple business and support units, each populated by highly trained, experienced executives. But often the efforts of individual units are not coordinated, resulting in conflicts, lost opportunities, and diminished performance.

Leave a comment

Filling Execution Gaps

Available Worldwide

Filling Exectution Gaps cover

Filling Execution Gaps is available worldwide. Below are some options.

 

PG DirectLogo
Limited Time Price $20.99
Amazon logo
Book or Kindle
Flag of the United States Canadian Flag Flag of the United Kingdom Irish Flag Deutsche Flagge
Drapeau Français Bandiera Italiana PRC flag
Japanese flag
Bandera de España
Flag of India
Bandera de México
Bandeira do Brasil
Flag of Australia
Vlag van Nederland
DeG Press Logo
Barnes and Noble Logo
Books a Million Logo
Booktopia Logo
Worldwide: Many other
book sellers worldwide.

Rescue The Problem Project

Internationally acclaimed

Image of RPP

For a signed and personalized copy in the US visit the our eCommerce website.

Amazon logo
Buy it in the United States Buy it in Canada Buy it in the United Kingdom
Buy it in Ireland Buy it in Germany Buy it in France
Buy it in Italy Buy it in the PRC
Buy it in Japan
Book sellers worldwide.

Other's References

More Info on Project Recovery

Tell me More!

Please send me more information
on fixing a failing project.

Upcoming Events

Sitemap